DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›News›Dredging on Indiana Harbor and Ship Canal Set for Next Summer (USA)
News

December 6, 2011 · about 14 years ago

Dredging on Indiana Harbor and Ship Canal Set for Next Summer (USA)

The Indiana Harbor and Ship Canal dredging is finally planned to commence next summer. Approximately 4.6 million cubic yards of sediment are intended to be removed from the harbor by the U.S. Army Corps of Engineers. The U.S. Environmental Protection Agency says that 362 toxic and cancer-causing sub

1 minutes read
  • LinkedIn
  • X
  • Email

The Indiana Harbor and Ship Canal dredging is finally planned to commence next summer. Approximately 4.6 million cubic yards of sediment are intended to be removed from the harbor by the U.S. Army Corps of Engineers. The U.S. Environmental Protection Agency says that 362 toxic and cancer-causing substances are present in the waterway.

Researchers keep undertaking their study to measure and check the toxic chemical levels.

During the annual two to six months of dredging operations, around 400,000 cubic yards of sediment will be displaced, says Natalie Mills, Army Corps project manager. The dredged material will be transported to the restricted disposal facility, which covers 186 acres of a former Sinclair Oil refinery.

Dredging works have not been conducted since 1972. Maintenance dredging is planned to be utilized during 25 years of the $150 million worth project, with 1.8 million cubic yards of sediment initially set to be removed.

Real-time air monitoring around the disposal site will be maintained by the Army Corps. The same is planned for the dock where sediment will be transferred from barges into the 21-foot-tall confinement facility.

[mappress]

Dredging Today Staff, December 6, 2011;

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

News

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free