Dredging Today
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Offshore Wind
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USA: Cuomo Announces Construction of New NY Bridge
Business & Finance

October 17, 2013 · about 12 years ago

USA: Cuomo Announces Construction of New NY Bridge

Governor Andrew M. Cuomo announced the beginning of formal construction of the New NY Bridge to replace the Tappan Zee with installation of the first permanent piles that will comprise the foundation of the new bridge. The bridge is scheduled to be completed in just under five years from the start o

2 minutes read
  • LinkedIn
  • X
  • Email

Governor Andrew M. Cuomo announced the beginning of formal construction of the New NY Bridge to replace the Tappan Zee with installation of the first permanent piles that will comprise the foundation of the new bridge.

The bridge is scheduled to be completed in just under five years from the start of formal construction making it one of the nation’s largest construction projects to be completed in such a short time.

“This week, we are putting shovels in the ground and starting formal construction on a new bridge to replace the Tappan Zee, the largest infrastructure project New York State has undertaken in decades, ” Governor Cuomo said. “After more than a decade of delay, New York State has moved this project forward at a dramatic pace while working with the community, involving the public and protecting the local environment. Once completed, drivers in Rockland, Westchester and surrounding areas will finally have a safer, less congested bridge that will include a walkway for pedestrians and bikers and accommodates future mass transit.”

Construction Timeline

– Dredging to prepare for bridge construction is ongoing until November 1, and will also take place during August, September and October, 2014.;

– October 2013: Main span permanent pile installation begins;

– November 2013: Permanent pile installation begins for approaches;

– March 2014: Work begins on approach substructure;

– June 2014: Work begins on main span substructure;

– September 2014: Work begins for erection of superstructure;

– Late 2014 / early 2015: Work begins on cable stay installation;

– Late 2016: Complete north span;

– December 2016: Relocate westbound traffic to new north span;

– February 2017: Relocate existing eastbound traffic to new north span;

– February 2017: Start demolition of existing bridge;

– Late 2017: Both spans complete;

– November 2017: Relocate eastbound traffic from new north span to new south span;

– April 2018: Physical completion of project;

– July 2018: Final acceptance of project.

More info

[mappress]

Press Release, October 17, 2013

Reach the Dredging Today industry in one go!

Dredging Today is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1EXCLUSIVE: IHC Equipment extends operational life of TSHD Biesbosch
  2. 2Dredging underway at Beach Haven West Complex
  3. 3Isle of Palms dredging update: Marinex makes steady progress
  4. 4GLDD’s dredger Liberty Island kicks off Buxton beach nourishment

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free