The Port of Wells dredging project is scheduled to commence on 10th March 2014.
The port’s dredging vessel “Kari Hege” will be engaged in the following dredging operations:
– Monday to Tuesday: in the main channel North of number 4 buoy, between buoys 4 & 2, and
– Wednesday to Friday: in the access channel to the Outer Harbour.
All material dredged from these areas will be placed on the berm, marked by the port hand channel buoys.
[mappress]
Press Release, March 7, 2014