Dredging Today
JobsNewsletter
Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Offshore Wind
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Phase Five of North Topsail Beach Project
Business & Finance

October 16, 2014 · about 11 years ago

Phase Five of North Topsail Beach Project

The North Topsail Beach Shoreline Protection Project is about to enter its fifth phase with the restoration works scheduled for early December 2014. This project was awarded to Norfolk Dredging on July 9, 2014. Construction works will start near 3588 Island Drive and go south toward the Surf City li

2 minutes read
  • LinkedIn
  • X
  • Email

The North Topsail Beach Shoreline Protection Project is about to enter its fifth phase with the restoration works scheduled for early December 2014. This project was awarded to Norfolk Dredging on July 9, 2014.

Construction works will start near 3588 Island Drive and go south toward the Surf City line. The design beach includes a 25 ft wide dune fronted by a 45 ft wide berm. The dune elevation is established at +14 ft NAVD and the berm elevation is +6 NAVD. Sufficient advance nourishment will also be placed to maintain the beach through the design life.

The average fill density to complete the project is approximately 75 cubic yards per linear foot for an estimated total fill volume of 1,500,000 CY. Material is proposed to be dredged from the offshore borrow area located approximately one-half to one and one-half miles offshore at the northern limits of Phase 5.

Future shoreline maintenance will be required to maintain the beach design on an approximate 5 year interval. Erosion trends calculated between 2005 and 2013 verify approximately 100,000 CY per year will be needed to sustain the 11.1 miles of shoreline in North Topsail Beach.

This volume is anticipated to be available through periodic maintenance of New River Inlet. Maintenance events are currently proposed on a 5 year interval and are expected to provide approximately 500,000 CY for each event. The first maintenance event is anticipated in FY17-18.

[mappress mapid=”18939″]

Press Release

Reach the Dredging Today industry in one go!

Dredging Today is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1VIDEO: Italdraghe SGT 200 CSD raises the bar in Guyana
  2. 2Manson nabs $12.9M Oakland dredging deal
  3. 3Maryland DNR provides funding for 24 public boating projects
  4. 4Queensland Government: Upper Warrill Creek flood resilience project begins

Related articles

Port of Vancouver: Dredging work at Second Narrows set for September
Business development

Port of Vancouver: Dredging work at Second Narrows set for September

about 1 month ago

United States to fund construction of Poti Seaport’s new berth
Berth Expansion

United States to fund construction of Poti Seaport’s new berth

about 1 month ago

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free

Related news

Port of Vancouver: Dredging work at Second Narrows set for September
Business development

Port of Vancouver: Dredging work at Second Narrows set for September

about 1 month ago
United States to fund construction of Poti Seaport’s new berth
Berth Expansion

United States to fund construction of Poti Seaport’s new berth

about 1 month ago