DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Venice Beach Dredging Resumes in March
Business & Finance

February 20, 2015 · about 11 years ago

Venice Beach Dredging Resumes in March

Sand placement on Venice Beach is temporarily delayed by a mechanical problem that’s caused the shutdown of dredging operations, the U.S. Army Corps of Engineers announced today. Dredging is tentatively scheduled to resume in early March. The beach renourishment project helps protect landside infras

1 minutes read
  • LinkedIn
  • X
  • Email

Sand placement on Venice Beach is temporarily delayed by a mechanical problem that’s caused the shutdown of dredging operations, the U.S. Army Corps of Engineers announced today. Dredging is tentatively scheduled to resume in early March.

The beach renourishment project helps protect landside infrastructure and property from storm damage. The side benefits of the project include providing habitat for shorebird and sea turtle nesting, and supporting local recreation and tourism.

The Corps contractor, Great Lakes Dredge & Dock (GLDD), has placed more than 294,000 cubic yards of sand on the beach to date. The completed project will place roughly 791,000 cubic yards of sand on 3.2 miles of Venice Beach shoreline. GLDD officials said they are still expecting to complete the project on time in early April.

Since the storms of 2012, dredging companies have generally worked non-stop to place sand on critically eroded beaches that will protect infrastructure along the Atlantic coastline.

This work, ongoing 24 hours daily and seven days a week, has likely taken a toll on vessels as well as other equipment. Last month the pump booster vessel, the Erin, was towed to Tampa for repairs and GLDD placed another booster on station.

On February 15, the Liberty Island, a trailing suction hopper dredge, received damage to its propellers. She sailed to dry dock in Mobile for repairs, and is tentatively scheduled to return between February 28 and March 3.

[mappress mapid=”19969″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free