The CT Department of Energy and Environmental Protection has released the latest update on the Mill River cleanup project in Fairfield, Connecticut.
TRC, the firm conducting the cleanup work for Exide, is currently in the process of dredging, dewatering the sediment, treating the filtrate water from the dewatering process, and discharging treated water back to the Mill River.
All of the sediment dewatering and water treatment work is occurring at the facility on Exide’s property at 2190 Post Road in Fairfield.
In May, the following activities will be conducted:
[mappress mapid=”20472″]