DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›New Timetable for Hanford Cleanup
Business & Finance

May 26, 2015 · about 11 years ago

New Timetable for Hanford Cleanup

The U.S. Environmental Protection Agency (EPA) and the Department of Energy (DOE) have reached a settlement over DOE’s failure to meet a critical September 2014 Tri-Party Agreement milestone for beginning sludge removal from K West Basin. The settlement includes an updated achievable and enforceable

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Environmental Protection Agency (EPA) and the Department of Energy (DOE) have reached a settlement over DOE’s failure to meet a critical September 2014 Tri-Party Agreement milestone for beginning sludge removal from K West Basin.

The settlement includes an updated achievable and enforceable timetable for beginning and completing sludge removal from the Basin.

According to Rick Albright, Director of EPA’s Superfund cleanup program in Seattle, the Agency is looking forward to seeing real progress on the K Basin cleanup.

Under the terms of the settlement, 10 other associated 100 K Area cleanup milestones affected by the delay in the start of sludge removal are being extended. A new milestone for completing installation of sludge transfer equipment has also been added.

The new milestone date for starting sludge removal is September 30, 2018. Sludge removal must now be completed by December 31, 2019. Other milestones that have been extended include the milestone to complete deactivation, demolition and removal of the K West Basin by 2023 and to complete all response actions in the K Area by 2024.

The 100 K Area is located along the Columbia River, and is one of six areas where plutonium production reactors operated during the Cold War. K East and K West Reactors operated in the 100 K Area.

Radioactive sludge, a result of corrosion on spent fuel stored in the basins for decades, has been consolidated in underwater storage containers in the K West Basin, with approximately 35 cubic yards of sludge remaining for removal.

[mappress mapid=”20559″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Boskalis, McLaughlin & Harvey complete Dover land reclamation
  2. 2Jones Bros wraps up Kinmel Bay coastal defense project
  3. 3RSGT, CMA CGM, Mawani invest big in Jeddah Islamic Port’s Terminal 4
  4. 4Rohde Nielsen completes maintenance dredging at Costa da Caparica

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free