DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›HDCC Starts Maalaea Project
Business & Finance

July 13, 2015 · about 11 years ago

HDCC Starts Maalaea Project

Hawaiian Dredging Construction Company (HDCC) has begun works on a $2.8 million project to remove and replace a badly deteriorated pier adjacent to the Maalaea Small Boat Harbor new ferry terminal building. When completed it will provide a new pier for the Lana‘i ferry and other vessels to load and

1 minutes read
  • LinkedIn
  • X
  • Email

Hawaiian Dredging Construction Company (HDCC) has begun works on a $2.8 million project to remove and replace a badly deteriorated pier adjacent to the Maalaea Small Boat Harbor new ferry terminal building.

When completed it will provide a new pier for the Lana‘i ferry and other vessels to load and unload passengers. It will complement the recently completed $16 million ferry and harbor improvement project by Hawaiian Dredging Construction Company.

The project scope of work includes the removal of existing fiberglass grating and steel frame; concrete pier decking and beams. The existing piles will be repaired and reused. The new pier will consist of reinforced concrete beams and decking; aluminum decking supported by an aluminum frame; and 4X10 reinforced plastic fendering to protect the new pier.

At a ground breaking ceremony last week, the contractor, Hawaiian Dredging Construction Company brought in a brand new excavator with a special auger attachment to drill the holes for the 24″ diameter cast-in-place concrete piles that will support the new piers.

The in-water work is scheduled to begin in July 2015, and the project will be completed in April 2016. Work on the ferry pier should not impact harbor users since the ferry pier has been closed for several months.

[mappress mapid=”20839″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Keyfield buys mega TSHD for $24.7M
  2. 2CHEC wins Escravos Channel dredging contract
  3. 3EXCLUSIVE: Eurovía del Guadalquivir dredging kicks off
  4. 4Brennan acquires Budrovich Contracting’s marine operations

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free