DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Newland Entities Bags Hamilton Levee Contract
Business & Finance

August 3, 2015 · about 11 years ago

Newland Entities Bags Hamilton Levee Contract

The U.S. Army Corps of Engineers, Sacramento District, awarded $6.2 million to Newland Entities Inc. of Marysville, California, on July 28, 2015, to begin levee construction this summer on the Hamilton City Flood Damage Reduction and Ecosystem Restoration project. The project, located approximately

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Sacramento District, awarded $6.2 million to Newland Entities Inc. of Marysville, California, on July 28, 2015, to begin levee construction this summer on the Hamilton City Flood Damage Reduction and Ecosystem Restoration project.

The project, located approximately 10 miles west of Chico, is the first in the nation to be authorized for construction under the Corps’ guidelines to develop multipurpose projects that include both flood risk reduction and ecosystem restoration.

“ This project truly is a multi-purpose project, ” said Nicole Ortega-Jewell, chief of civil works project management for the Sacramento District . “ We’re giving the river the extra room it naturally wants to take to reduce flood risk, while at the same time, invigorating a large area of wildlife.”

Divided into two construction phases, the $67.9 million project will construct a new 6.8-mile setback levee, designed to not only lower flood risk for Hamilton City, but also reconnect and restore nearly 1,500 acres of natural habitat once separated by the deteriorated existing “J” levee.

This first phase will tie into the existing “J” levee on the southern side of Dunning Slough and construct the southern half of the levee. Work is expected to begin this fall and be complete by fall 2016.

When funded, the remaining work will begin construction two miles north of Hamilton City and end at its interface with the Phase 1 levee at Dunning Slough as well as complete the ecosystem restoration component.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Keyfield buys mega TSHD for $24.7M
  2. 2CHEC wins Escravos Channel dredging contract
  3. 3EXCLUSIVE: Eurovía del Guadalquivir dredging kicks off
  4. 4Brennan acquires Budrovich Contracting’s marine operations

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free