DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Preparations Underway for Hilton Head Island Beachfill
Business & Finance

January 21, 2016 · about 10 years ago

Preparations Underway for Hilton Head Island Beachfill

The preliminary activities associated with the 2016 Beach Nourishment Project will start in the upcoming weeks, the Town of Hilton Head Island said in an announcement yesterday. In particular, pre-project surveys of both the beach and the offshore borrow sites will be conducted. Both land and water

2 minutes read
  • LinkedIn
  • X
  • Email

The preliminary activities associated with the 2016 Beach Nourishment Project will start in the upcoming weeks, the Town of Hilton Head Island said in an announcement yesterday.

In particular, pre-project surveys of both the beach and the offshore borrow sites will be conducted.

Both land and water based survey crews will be present and active within the project limits and offshore at the Barrett and Bay Point Shoal borrow sites.

The mobilization of equipment and requisite pipeline will take place during February. As a result, a portion of the Islanders’ Beach Park parking lot and beach front will be closed to the public for use by the dredge contractor.

This Town-owned facility has been designated as one of three construction equipment access points for the project.

The initial project schedule indicates that the placement of sand will start on March 1, 2016, at South Beach, near the Tower Beach Club in the Sea Pines Resort.

Once work is complete at South Beach, the placement of fill is then scheduled to begin around March 23, 2016 on the Atlantic Oceanfront, near the Marriott’s Grande Ocean Resort in South Forest Beach.

Work will proceed to the north toward the Sonesta Resort. Therefore, it is expected that the beach fill related activities including mobilization of pipeline and active fill placement will be in the vicinity of South and North Forest Beach from mid to late March through mid to late April.

Upon completion of this portion of the work, the dredger is expected to be repositioned to the Bay Point Shoal with work then commencing at Singleton Beach, just south of the Folly around May 2, 2016. Work will advance to the south.

Work along the entirety of the Palmetto Dunes shoreline is expected to occur between May 2 and May 26.

Lastly, all work adjacent to the Atlantic Ocean and Port Royal Sound on the Port Royal Plantation shoreline, immediately southeast and northwest of the Port Royal Beach House is scheduled for June.

[mappress mapid=”21836″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Keyfield buys mega TSHD for $24.7M
  2. 2CHEC wins Escravos Channel dredging contract
  3. 3EXCLUSIVE: Eurovía del Guadalquivir dredging kicks off
  4. 4Brennan acquires Budrovich Contracting’s marine operations

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free