DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Boskalis to Restore Depth in Aberdeen Harbor
Business & Finance

February 18, 2016 · about 10 years ago

Boskalis to Restore Depth in Aberdeen Harbor

Much of the damage caused by Storm Frank, which hit the North East of Scotland on the 30th of December last year, has been well publicized in the press. In particular, the impact of the rise in height and flow rate of the River Dee, was very apparent to all. What has been less visible […]

2 minutes read
  • LinkedIn
  • X
  • Email

Much of the damage caused by Storm Frank, which hit the North East of Scotland on the 30th of December last year, has been well publicized in the press.

In particular, the impact of the rise in height and flow rate of the River Dee, was very apparent to all. What has been less visible is the damage, caused by the storm, to Aberdeen Harbor.

The resulting remedial work, which has begun, will address the loss of depth, caused by circa 28,000 cubic meters of material being washed down the River Dee during the storm, and deposited on the harbor floor. This material needs to be removed so that the required water depth is restored.

Simultaneously, the work will address the ‘over depth’ damage caused by the storm. This is when the increased flow of the river causes ‘scouring’ to the harbor floor, resulting in ‘dips’ in certain areas and a subsequent increased in water depth. Circa 14,000 tonnes of fill material will therefore be imported into the harbor to level these areas out.

Fortunately, all of this damage is confined to the west of the navigation channel and away from the main areas of vessel activity. The overall damage is also minimal considering the exceptional weather conditions experienced, and the harbor infrastructure generally weathered the storm well.

Vessels involved in the remedial work include Boskalis Westminster’s backhoe dredger ‘Manu Pekka’ and other support vessels.

The work is estimated to take approximately 20 days.

[mappress mapid=”21981″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Keyfield buys mega TSHD for $24.7M
  2. 2CHEC wins Escravos Channel dredging contract
  3. 3EXCLUSIVE: Eurovía del Guadalquivir dredging kicks off
  4. 4Brennan acquires Budrovich Contracting’s marine operations

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free