DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Lewisville Lake Dam Repair Work Underway
Business & Finance

March 8, 2016 · about 10 years ago

Lewisville Lake Dam Repair Work Underway

The U.S. Army Corps of Engineers, Fort Worth District, continues its efforts to repair the 161-foot long embankment slide which occurred during the floods last year at the Lewisville Lake Dam. Bristol General Contractors, LLC, the slide repair contractor, has been on site since last month and is con

1 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Fort Worth District, continues its efforts to repair the 161-foot long embankment slide which occurred during the floods last year at the Lewisville Lake Dam.

Bristol General Contractors, LLC, the slide repair contractor, has been on site since last month and is constructing haul roads on government property next to the dam and has moved in their construction office trailer for on-site supervision of the $6.4 million repair of the embankment slide.

“The reconstructed embankment will be protected by stone riprap on the upstream side and Bermuda grass sod on the downstream side, ” said project manager, Mike Kingston . “As part of this effort, removal and replacement of a portion of the asphalt roadway and subgrade layers along the embankment crest will be required.”

The slide was discovered within hours of occurring during the flood event in late June by lake personnel who were monitoring the dam around the clock due to the high pool levels. These types of slides are typical on earthen-rolled dams but do require attention to ensure the continued integrity of the structure.

The $6.4 million project is scheduled for completion this summer.

[mappress mapid=”22063″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Keyfield buys mega TSHD for $24.7M
  2. 2CHEC wins Escravos Channel dredging contract
  3. 3EXCLUSIVE: Eurovía del Guadalquivir dredging kicks off
  4. 4Brennan acquires Budrovich Contracting’s marine operations

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free