DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Team Van Oord Completes Teignmouth Sea Wall Repairs
Business & Finance

April 7, 2016 · about 10 years ago

Team Van Oord Completes Teignmouth Sea Wall Repairs

Three months after winter storms damaged a section of Teignmouth’s promenade, the Environment Agency together with the contractors successfully completed repair works on the sea wall. The agency worked with Teignbridge District Council and contractors Team Van Oord to repair the sea wall and secure

1 minutes read
  • LinkedIn
  • X
  • Email

Three months after winter storms damaged a section of Teignmouth’s promenade, the Environment Agency together with the contractors successfully completed repair works on the sea wall.

The agency worked with Teignbridge District Council and contractors Team Van Oord to repair the sea wall and secure it for the future.

During the work a granite ‘obelisk’ – thought to be a marker stone dating back to 1874 – was discovered on the beach.

Conditions during the repair work were challenging, with continued storms, bad weather, and access for machinery only possible on the low tides around spring tides. The crews were only able to work on the beach for a few hours at a time, for a few days at a time, and often had to work during the night.

Thom Buxton-Smith, for the Environment Agency , said: “ Despite these challenges we worked with Team Van Oord to complete the repairs quickly. The voids have been filled beneath the promenade, slipway and car park. We have repaired the limestone masonry sea wall and installed steel sheet piling at the base of the wall to stabilize it. ”

The promenade was re-opened to the public in time for the Easter weekend and the remaining fencing and site equipment will be removed by the end of this week.

[mappress mapid=”22186″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Keyfield buys mega TSHD for $24.7M
  2. 2CHEC wins Escravos Channel dredging contract
  3. 3EXCLUSIVE: Eurovía del Guadalquivir dredging kicks off
  4. 4Brennan acquires Budrovich Contracting’s marine operations

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free