DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USACE to Hold Public Meeting on Indiana Harbor Dredging
Business & Finance

May 20, 2016 · about 10 years ago

USACE to Hold Public Meeting on Indiana Harbor Dredging

The U.S. Army Corps of Engineers and East Chicago Waterway Management District will hold a public meeting to present this year’s Indiana Harbor and Canal dredging schedule and activities. This event will take place on Wednesday, June 15, 2016, at City Hall, Annex Building in East Chicago, Indiana. T

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers and East Chicago Waterway Management District will hold a public meeting to present this year’s Indiana Harbor and Canal dredging schedule and activities.

This event will take place on Wednesday, June 15, 2016, at City Hall, Annex Building in East Chicago, Indiana.

The current dredging and confined disposal facility (CDF) operation is being conducted by a joint venture between Durocher Marine (a division of Kokosing Construction Company, Inc.) and O’Brien & Gere.

This contract started in 2011 and will end on September 30, 2016. These dredging operations are scheduled to be completed before September 30.

A new dredging and CDF operation contract will then be awarded to continue work from October 1, 2016, to September 30, 2021.

Project Description:

The existing navigation project consists of a harbor channel ranging in depth from 27 to 29 feet LWD and 2 canals with depths of 22 feet.

Contaminated sediment and a lack of a suitable storage place for the sediment lead to the harbor not being dredged from 1972 to 2012.

Since 2012, nearly 1 million cy of sediment has been removed from the waterway and confined, greatly reducing the contaminants that had previously been washing into Lake Michigan and improving the efficiency of deep draft commercial navigation.

Under the project, the entire federal channel will be dredged to congressionially authorized navigation depths, including the removal of sediments in adjacent berthing and docking areas at the local sponsors (non-federal) expense.

The scheme includes the operation and maintenance of the confined disposal facility (CDF) on an USEPA Resource Conservation and Recovery Act (RCRA) site in East Chicago, Indiana.

In addition to providing storage for the dredged sediment, the CDF isolates and contains the existing on-site soil and groundwater contamination in compliance with RCRA requirements.

[mappress mapid=”22400″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Keyfield buys mega TSHD for $24.7M
  2. 2CHEC wins Escravos Channel dredging contract
  3. 3EXCLUSIVE: Eurovía del Guadalquivir dredging kicks off
  4. 4Brennan acquires Budrovich Contracting’s marine operations

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free