DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USACE Proposes Housatonic River Maintenance Dredging
Business & Finance

June 14, 2016 · about 10 years ago

USACE Proposes Housatonic River Maintenance Dredging

The U.S. Army Corps of Engineers, New England District is proposing to perform maintenance dredging of portions of the Housatonic River Federal Navigation Project in Stratford and Milford, Conn. The proposed work involves removal of up to 300,000 cubic yards of sandy material from portions of the 18

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, New England District is proposing to perform maintenance dredging of portions of the Housatonic River Federal Navigation Project in Stratford and Milford, Conn.

The proposed work involves removal of up to 300,000 cubic yards of sandy material from portions of the 18-foot main channel. The state of Connecticut is the sponsor for this proposed work.

“Natural shoaling processes and storm events have reduced available depths in the lower sections of the Housatonic River. The 18-foot-deep authorized channel has numerous areas that have shoaled above the -18 foot mean lower low water plane ,” said Project Manager Jack Karalius , of the Corps’ New England District, Programs and Project Management Division in Concord, Mass.

“Some areas have shoaled to as shallow as -5 feet mean lower low water.”

The existing Federal navigation project provides for an 18-foot deep, 200-foot wide main channel from the mouth of the river to the lower end of Culvers Bar (approximately five miles distance).

Maintenance dredging will be required in order to restore most of the authorized depth and width of the channel. Both recreational and commercial vessels transit the river.

More than 1,000 vessels are based in the river and harbor, including approximately 15 commercial vessels.

Maintenance dredging will be performed using either a mechanical dredge or hopper dredge. The dredged sand will be transported and pumped directly onto Hammonasset Beach State Park in Madison to renourish the eroding beach.

The proposed work will be performed over an approximately three to four month period between Oct. 1 and Jan. 31 for shoals inside Milford Point, and between Oct. 1 and Feb. 28 for shoals seaward of Milford Point, in the year in which funds become available and necessary approvals are received.

[mappress mapid=”22540″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Boskalis, McLaughlin & Harvey complete Dover land reclamation
  2. 2Jones Bros wraps up Kinmel Bay coastal defense project
  3. 3RSGT, CMA CGM, Mawani invest big in Jeddah Islamic Port’s Terminal 4
  4. 4Rohde Nielsen completes maintenance dredging at Costa da Caparica

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free