DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Sand Placement Activities Underway at Port Royal Plantation
Business & Finance

July 11, 2016 · about 10 years ago

Sand Placement Activities Underway at Port Royal Plantation

The Town of Hilton Head Island has just announced the latest update on their 2016 Beach Nourishment Project. Currently, the Town’s contractor, Weeks Marine, Inc., is working at the “heel” of the Island adjacent to Port Royal Plantation. To date, more than 450,000 cubic yards of sand have been placed

1 minutes read
  • LinkedIn
  • X
  • Email

The Town of Hilton Head Island has just announced the latest update on their 2016 Beach Nourishment Project.

Currently, the Town’s contractor, Weeks Marine, Inc., is working at the “heel” of the Island adjacent to Port Royal Plantation.

To date, more than 450,000 cubic yards of sand have been placed since the project’s June 17, 2016 start.

It is expected that work will continue at Port Royal for the next 5-7 days.

In preparation for the commencement of sand placement activities at South Beach later this month, hydrographic survey crews operating in boats collecting data will start its work today afternoon around the time of high tide.

The area of interest includes the nearshore waters between Brown Pelican Road and Marsh Wren Road.

The survey work is expected to be completed no later than July 13.

During the 5 month beachfill project, worth $20.7 million, construction operations will proceed around the clock and will, on average, move along the shoreline at a rate of about 200 to 300 feet per day.

[mappress mapid=”22682″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Boskalis, McLaughlin & Harvey complete Dover land reclamation
  2. 2Jones Bros wraps up Kinmel Bay coastal defense project
  3. 3RSGT, CMA CGM, Mawani invest big in Jeddah Islamic Port’s Terminal 4
  4. 4Rohde Nielsen completes maintenance dredging at Costa da Caparica

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free