DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Preparations Underway for Longboat Key Nourishment Project
Business & Finance

August 15, 2016 · about 10 years ago

Preparations Underway for Longboat Key Nourishment Project

Norfolk Dredging Company (NDC) of Chesapeake, VA began mobilizing its equipment to the south end of Longboat Key on August 8th to start construction of the New Pass Dredging and Beach Nourishment Project. Supply barges, a crane barge and shorepipe will arrive at New Pass by tomorrow, according to th

1 minutes read
  • LinkedIn
  • X
  • Email

Norfolk Dredging Company (NDC) of Chesapeake, VA began mobilizing its equipment to the south end of Longboat Key on August 8th to start construction of the New Pass Dredging and Beach Nourishment Project.

Supply barges, a crane barge and shorepipe will arrive at New Pass by tomorrow, according to the Town of Longboat Key’s latest announcement.

Equipment, shorepipe, and a temporary beach office will be delivered by crane over the south terminal groin and onto the beach in the vicinity of Sands Point Condominium and The Resort at Longboat Key Club to be hauled northward along the shoreline to the L’Ambiance beach area.

Other smaller equipment will be delivered to the beach through a temporary beach access easement and secured on the beach at L’Ambiance.

From Tuesday, August 16th through Friday, August 19, the mobilization schedule will include pipeline and equipment assembly, subline installation and discharge pipeline placement on the beach.

The Pullen, a 150-foot-long cutterhead-pipeline hydraulic dredge, is expected to arrive in the area on August 19th and begin dredging, weather permitting.

The sand dredged from the New Pass channel borrow area will be delivered via a submerged pipeline to the southern L’Ambiance Condominium boundary and begin building the beach northward to Regent Place.

Dredging operations will take place 24/7 to complete this work as quickly as possible.

[mappress mapid=”22862″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free