DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Coastline Consulting Bags Mianus River Dredging Contract
Business & Finance

September 21, 2016 · about 10 years ago

Coastline Consulting Bags Mianus River Dredging Contract

Maintenance dredging of the Mianus River Federal Navigation Channel in Greenwich, Conn., will be completed under the terms of a $2.2 million contract recently awarded by the U.S. Army Corps of Engineers, New England District. Work will be accomplished by Coastline Consulting and Development, LLC of

1 minutes read
  • LinkedIn
  • X
  • Email

Maintenance dredging of the Mianus River Federal Navigation Channel in Greenwich, Conn., will be completed under the terms of a $2.2 million contract recently awarded by the U.S. Army Corps of Engineers, New England District.

Work will be accomplished by Coastline Consulting and Development, LLC of Branford, Conn.

Dredging is scheduled to start on or about October 11, 2016 and take about 3 months to complete. The contract was awarded on September 14, 2016.

The state of Connecticut is funding the entire project and signed a memorandum of agreement with the Corps so that this work could be completed.

“This project consists of mechanically dredging approximately 50,000 cubic yards of fine-grain clay and silt from the authorized 6-foot deep, by 100-foot wide Federal channel, ” said Project Manager Jack Karalius, of the Corps’ New England District, Programs and Project Management Division in Concord, Mass.

“The dredged material will be disposed of using open water placement approximately 8 miles from the project site.”

The dredging window, due to environmental constraints, is October 1 to January 31.

The last time the channel was maintained was in 1985 when approximately 52,000 cubic yards of sediment were removed.

[mappress mapid=”23018″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free