DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›San Luis Rey River Dredging Project Postponed
Business & Finance

November 3, 2016 · about 9 years ago

San Luis Rey River Dredging Project Postponed

The San Luis Rey River dredging project, scheduled to take place this fall, will be postponed until next year, The Coast News Group reports. Greg Fuderer, Army Corps senior public affairs specialist, said in late September that dredging would be postponed for a needed permit, but would likely procee

1 minutes read
  • LinkedIn
  • X
  • Email

The San Luis Rey River dredging project, scheduled to take place this fall, will be postponed until next year, The Coast News Group reports.

Greg Fuderer, Army Corps senior public affairs specialist, said in late September that dredging would be postponed for a needed permit, but would likely proceed this year.

The decision was recently made to wait until next year, according to The Coast News.

The needed permit is expected to be approved at the end of the month. Once the permit is in hand project bids will begin, and dredging will start in January 2017.

The project, set to take place from just west of Benet Road to east of Foussat Road, aims to remove 230,000 cubic yards of sediment from the river to increase its flow capacity to 710,200 cubic feet of water per second.

The overall goal of this cleanup scheme is to provide for 100-year flood protection for neighborhoods along the river, said Fuderer.

Once it begins, the work is expected to take several months to complete.

[mappress mapid=”23211″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free