The Environment Agency and Teignbridge District Council (TDC) are working together on the Dawlish Warren beach management scheme.
The main scheme is due to begin in 2017, but due to significant damage suffered to the groynes during the storms of winter 2015/16 a package of emergency works was completed in spring 2016.
Over the summer of 2016, a further program of refurbishment and maintenance works was completed, focusing on groynes 5 to 9.
Setting up the construction site will start in January 2017 with the works lasting approximately 9 months.
During the beach recharge works certain areas of the beach will be closed to ensure public safety, but every effort will be made to ensure public access to the amenities at Dawlish Warren.
Key dates: