DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Prock Marine Wins Sagamore Creek Dredging Deal
Business & Finance

December 1, 2016 · about 9 years ago

Prock Marine Wins Sagamore Creek Dredging Deal

A portion of the Congressionally-authorized Back Channels portion of the Portsmouth Harbor and Piscataqua River Federal navigation project known as “Sagamore Creek” in Portsmouth and Rye, New Hampshire, will undergo maintenance dredging under the terms of a $542,970.00 contract issued recently by th

1 minutes read
  • LinkedIn
  • X
  • Email

A portion of the Congressionally-authorized Back Channels portion of the Portsmouth Harbor and Piscataqua River Federal navigation project known as “Sagamore Creek” in Portsmouth and Rye, New Hampshire, will undergo maintenance dredging under the terms of a $542,970.00 contract issued recently by the USACE’s, New England District.

Work will be accomplished by Prock Marine Company of Rockland, Maine.

The dredging operations are scheduled to start on or about January 10, 2017 and take about 4 to 6 weeks to complete. The contract was awarded on November 18, 2016.

“Approximately 4,300 cubic yards of predominantly sandy sediment will be dredged from the confluence of the three 6-foot navigation channels by mechanical dredge,” said Project Manager Mike Walsh, of the Corps’ New England District, Programs and Project Management Division in Concord, Mass.

“The sandy dredge material will be transported by scow and disposed of at a nearshore placement site adjacent to Wallis Sands Beach.”

The dredging is needed to restore that portion of the navigation project to authorized dimensions and alleviate shoal conditions that are impacting safe navigation. The work is scheduled to be completed before March 1 to minimize impact to natural resources in the area.

The project will be managed by the Corps under the supervision of a Corps’ Quality Assurance Representative to assure compliance with contract requirements.

[mappress mapid=”23323″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free