DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Next Phase of Ngatea Flood Protection Scheme Kicks Off
Business & Finance

February 20, 2017 · about 9 years ago

Next Phase of Ngatea Flood Protection Scheme Kicks Off

The next stage of Waikato Regional Council’s multi million dollar project to strengthen Piako’s flood protection scheme has just kicked off near Ngatea. Work costing $1.3 million started this month at the Rawerawe floodgate at the end of River Road, and will continue along the river towards the town

1 minutes read
  • LinkedIn
  • X
  • Email

The next stage of Waikato Regional Council’s multi million dollar project to strengthen Piako’s flood protection scheme has just kicked off near Ngatea.

Work costing $1.3 million started this month at the Rawerawe floodgate at the end of River Road, and will continue along the river towards the township.

It is expected to take local contractors Kerepehi Transport Limited until mid-April to raise the height of the stopbank, with crews working up to 12 hours a day, six days a week.

“The existing stopbank is either at or below our desired height, and this top up is going to increase it to 500mm above the design flood level,” said senior engineer, Dan du Toit.

“It means that even when the stopbank naturally sinks over time, Ngatea’s residents will continue to be protected from the risk of flooding.”

This scheme is part of a long term project for the area which started in 2011 with this section undergoing river stability works.

These works were successfully completed this year – two years ahead of schedule – allowing the council to move to the next stage of this project, raising the height of the stopbanks.

[mappress mapid=”23626″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free