DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Ribbon Cutting Ceremony Set for Muddy River Project
Business & Finance

April 18, 2017 · about 9 years ago

Ribbon Cutting Ceremony Set for Muddy River Project

Federal, state and local partners will mark the completion of Phase 1 of the $30.9 million Muddy River Flood Risk Management project in a ribbon cutting ceremony of the Justine Mee Liff Park on April 21, 2017 in Boston, the U.S. Army Corps of Engineers just announced. The Muddy River project was in

2 minutes read
  • LinkedIn
  • X
  • Email

Federal, state and local partners will mark the completion of Phase 1 of the $30.9 million Muddy River Flood Risk Management project in a ribbon cutting ceremony of the Justine Mee Liff Park on April 21, 2017 in Boston, the U.S. Army Corps of Engineers just announced.

The Muddy River project was in response to a storm event in 1996 that resulted in overtopping of the banks of the Muddy River as well as several tributary areas, particularly Stony Brook. The stormwater that was not contained by the Muddy River caused severe flooding and extensive damage to the Green Line Station of the MBTA, local hospitals, schools and homes.

The city of Boston, town of Brookline and the Commonwealth of Massachusetts proposed a plan called “the Emerald Necklace Environmental Improvements Master Plan, Phase I Muddy River Flood Control, Water Quality and Habitat Enhancement,” in January 1999.

The Water Resources Development Act (WRDA) of 1999 authorized the Corps of Engineers to evaluate this Master Plan which led to the development of the Decision Document and Environmental Assessment in 2003 with the recommended plan.

The objectives of the plan were to increase flood control, improve water quality and enhance aquatic/riparian habitat within the Muddy River by dredging accumulated sediment, providing flood damage reduction through improvements to restrictive drainage culverts, removing nuisance vegetation, improving fisheries/wildlife habitat and water quality, bank stabilization and promoting and enhancing recreational use of Emerald Necklace parklands.

[mappress mapid=”23933″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free