DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Town of Wellfleet Seeks USACE’s Permit for Harbor Dredging
Business & Finance

May 23, 2017 · about 9 years ago

Town of Wellfleet Seeks USACE’s Permit for Harbor Dredging

The town of Wellfleet is seeking a permit from the U.S. Army Corps of Engineers, New England District, to conduct work in waters of the U.S. in order to dredge in Wellfleet Harbor at Kendrick Avenue in Wellfleet, Mass. The proposed work involves maintenance dredging of all town-managed channels and

2 minutes read
  • LinkedIn
  • X
  • Email

The town of Wellfleet is seeking a permit from the U.S. Army Corps of Engineers, New England District, to conduct work in waters of the U.S. in order to dredge in Wellfleet Harbor at Kendrick Avenue in Wellfleet, Mass.

The proposed work involves maintenance dredging of all town-managed channels and anchorage areas in Wellfleet Harbor to -6 feet mean low water (MLW), with 1 foot over-dredge.

A total area of approximately 38.5 acres will be mechanically dredged and produce approximately 378,300 cubic yards of sandy sediment for disposal at the Cape Cod Bay Disposal Site.

Area 1, which is comprised of the North and South Access Channels, the North Anchorage, and the L-Pier Access Channel, is 14.6 acres, will produce 118,300 cubic yards, and was last dredged in 2001. Approximately 2.4 acres, or 16%, of Area 1 is intertidal flats, USACE said.

Area 2, which is the south anchorage, is 23.8 acres, will produce 248,000 cubic yards, and was last dredged in 1957. Approximately 13.9 acres, or 58%, of Area 2 is intertidal flats.

Through the development of this project, the applicant has attempted to avoid and minimize direct impacts to waters of the U.S. The Corps continues to work with the applicant to minimize temporary construction impacts (noise and turbidity impacts) to waters of the U.S.

Public comments on this work proposed by the town of Wellfleet should be submitted no later than June 23, USACE said.

[mappress mapid=”24104″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free