DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Sediment Removal Starts at Harris Avenue Shipyard Site
Business & Finance

July 5, 2017 · about 9 years ago

Sediment Removal Starts at Harris Avenue Shipyard Site

Contractors have begun an environmental cleanup project to remove contamination at the Harris Avenue Shipyard site on Bellingham Bay, reported yesterday Washington State Department of Ecology. According to WDOE, crews will remove contaminated sediment, soil, and treated wood from a portion of the si

1 minutes read
  • LinkedIn
  • X
  • Email

Contractors have begun an environmental cleanup project to remove contamination at the Harris Avenue Shipyard site on Bellingham Bay, reported yesterday Washington State Department of Ecology.

According to WDOE, crews will remove contaminated sediment, soil, and treated wood from a portion of the site.

The contamination is from past shipbuilding and maintenance activities, and is not related to current shipyard operations.

Approximately 1,300 cubic yards of contaminated soil and 10,200 cubic yards of contaminated sediment will be taken from the site. Workers will also demolish an existing wood building and creosote-treated wood pier. Crews will then install a concrete pier supported by steel pilings.

Tests have found soil and sediment at the site contaminated with heavy metals, polychlorinated biphenyls (PCBs), phthalates, polycyclic aromatic hydrocarbons, semivolatile organic compounds, and petroleum hydrocarbons.

Soil removal is underway and in-water construction activities will start August 1. The project is expected to finish mid-2019.

The Port of Bellingham cleanup project is expected to cost about $14 million. The project addresses about one third of the 10-acre Harris Avenue Shipyard site. A cleanup plan for the entire site is expected to be complete within the next two years.

[mappress mapid=”24253″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free