DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USACE Everglades Update: Milestone for Biscayne Bay
Business & Finance

July 12, 2017 · about 9 years ago

USACE Everglades Update: Milestone for Biscayne Bay

The U.S. Army Corps of Engineers, Jacksonville District, recently completed a construction contract laying the groundwork to reestablish freshwater flow to Biscayne Bay as part of ongoing efforts to restore America’s Everglades. The Corps completed construction on the L-31E Flow-way Culverts S-712A

1 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Jacksonville District, recently completed a construction contract laying the groundwork to reestablish freshwater flow to Biscayne Bay as part of ongoing efforts to restore America’s Everglades.

The Corps completed construction on the L-31E Flow-way Culverts S-712A and S-712B on June 29, 2017, two weeks ahead of schedule.

The nearly $780,000 construction contract was awarded in September 2016 to Sweat, LLC from Orange Park, Florida, said USACE.

Construction of the culverts will allow water to flow from the L-31E Canal to adjacent wetlands as part of the Biscayne Bay Coastal Wetlands Phase I Project in Miami-Dade County.

“With the completion of this construction contract, we are initiating efforts to improve the flow of water into Biscayne Bay and the southern Everglades ecosystem,” said April Patterson, USACE project manager. “The L-31E Flow-way culverts are an important first step and will allow freshwater flows to Biscayne Bay’s coastal wetlands.”

The Biscayne Bay Coastal Wetlands Phase I Project is a component of the Comprehensive Everglades Restoration Plan (CERP), the U.S. Army Corps of Engineers’ largest ecosystem restoration program, conducted in partnership with the South Florida Water Management District.

Construction of the remaining three contracts, two L-31E Flow-way contracts and the Cutler Wetlands contract, will redistribute available surface water from the existing canal network to wetlands located east and west of the L-31E Levee through a spreader canal system, said USACE.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free