DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Lahaina Harbor Dredging on the Way
Business & Finance

September 25, 2017 · about 9 years ago

Lahaina Harbor Dredging on the Way

The Department of Land and Natural Resources of the State of Hawaii will hold a public information meeting to explain to Maui boaters and community the project scope and planned fall schedule for maintenance dredging at Lahaina Harbor and Mala Boat Ramp. The meeting is scheduled for today from 5 to

2 minutes read
  • LinkedIn
  • X
  • Email

The Department of Land and Natural Resources of the State of Hawaii will hold a public information meeting to explain to Maui boaters and community the project scope and planned fall schedule for maintenance dredging at Lahaina Harbor and Mala Boat Ramp.

The meeting is scheduled for today from 5 to 6:30 p.m. at the West Maui Senior Center, in Lahaina.

According to DLNR, the American Marine Corporation will this week begin mobilizing equipment on-site and preparing the dewatering site by installing the necessary best management practices, such as dust fencing for dredge materials at Mala and full depth silt curtain for in-water work.

In-water dredging at Mala Boat Ramp is scheduled to start October 9 and be completed by October 20. Dredging will then start at Lahaina on October 23 and be completed by December 29.

This $1.2 million dredging project will deepen the currently shallow harbor entrance channel, which is critical for safe passage of boat traffic in and out of the harbor.

The dredging work will take place Monday through Thursday from 6:30 a.m. to 5 p.m. The contractor will keep both Mala Boat Ramp and the Lahaina SBH entrance channels accessible throughout the construction period.

The project will consist of removal, transportation, stockpiling, dewatering, and disposal of approximately 5,000 to 7,000 cubic yards of sediment from the Lahaina Small Boat Harbor entrance channel and mooring, and approximately 1,000 to 2,000 cubic yards of sediment from the Mala Boat Ramp basin and entrance channel.

Lahaina small boat harbor was last dredged in 2012.

[mappress mapid=”24430″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free