DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›WA Government to Support Broome Channel Works
Business & Finance

October 17, 2017 · about 8 years ago

WA Government to Support Broome Channel Works

Kimberley Ports Authority announced recently that the State Government has committed funding to carry out channel and turning basin works at the Port of Broome in readiness for the 2019 cruise season. CEO Kevin Schellack said, “Channel work investigations are in the early stages and consultants BMT

2 minutes read
  • LinkedIn
  • X
  • Email

Kimberley Ports Authority announced recently that the State Government has committed funding to carry out channel and turning basin works at the Port of Broome in readiness for the 2019 cruise season.

CEO Kevin Schellack said, “ Channel work investigations are in the early stages and consultants BMT JFA have provided a scope of works and listed the feasibility studies required before the extent of works can be fully identified .”

Current estimates show that 70,000 cubic meters of material may need to be removed from the channel. KPA is investigating a small amount of dredging adjacent to and north of the wharf totaling an additional 15,000 cubic meters of material to be removed.

According to KPA, environmental studies have begin with the lodgement of a Sampling Analysis Plan to the Federal Department of Environment and Energy for review and approval. Sediment samples are to be completed in late October and will then undergo laboratory testing to ensure there are no contaminants in the dredge material.

A small jack up barge will be utilized in November to complete the geophysical survey by drilling boreholes to determine the properties of the dredge material. To complete the detailed channel design data collectors for the Metocean studies will be deployed in the channel to determine real time tidal and wave data.

Final feasibility reports may need to be provided to both Federal and State government agencies for approvals, this is still to be determined as the studies progress. A final approved detailed Channel Design would enable the project to proceed, added KPA.

Kimberley Ports Authority concluded that at this stage it is most likely that a cutter suction dredge will be able to complete the works. If sea dumping is deemed appropriate KPA will apply for a sea dumping permit to place spoil in the deeper parts of the existing channel near the dredging site to minimize the area of disturbance.

[mappress mapid=”24508″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free