DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Gowanus Canal Dredging Scheme Underway
Business & Finance

October 24, 2017 · about 8 years ago

Gowanus Canal Dredging Scheme Underway

Earlier this month, contractors working for the Environmental Protection Agency began work on a dredging and capping pilot study in the Gowanus Canal’s 4th Street Turning Basin. The process involves installation of steel sheeting in front of existing bulkheads, followed by dredging of contaminated s

2 minutes read
  • LinkedIn
  • X
  • Email

Earlier this month, contractors working for the Environmental Protection Agency began work on a dredging and capping pilot study in the Gowanus Canal’s 4th Street Turning Basin.

The process involves installation of steel sheeting in front of existing bulkheads, followed by dredging of contaminated sediment from the canal, before the installation of a multi-layered protective cap at the bottom of the canal.

The EPA expects to complete this pilot effort in the Spring of 2018.

The results of the study will be used to evaluate and finalize the elements for the dredging and capping of the entire canal.

In October 2016, the first phase of work performed in the turning basin, which consisted of the removal of debris from the bottom of the basin, was completed.

This second phase of work, referred to as the Dredging and Capping Pilot Study, will include dredging contaminated sediment from the turning basin and installing a multi-layer protective cover or cap on the original canal bottom.

Contaminated sediment removed during dredging will be transported via barge for processing at the staging area location (the secured open lot at Smith and Huntington streets which is part of the Citizens MGP State Superfund site).

“ There, water drained from the dredged sediment will be removed from the barge and environmentally treated before being discharged to the canal, ” EPA said.

Cement-like material will then be added to the dewatered contaminated sediment in order to stabilize it prior to transport via barge to off-site licensed disposal facilities.

[mappress mapid=”24545″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free