DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Sunny Isles Beach Renourishment Starts
Business & Finance

October 30, 2017 · about 8 years ago

Sunny Isles Beach Renourishment Starts

The U.S. Army Corps of Engineers, Jacksonville District, said in its latest release that the Sunny Isles Beach renourishment project is set to kick off. The $8.6 million project is part of the Miami-Dade County Beach Erosion Control and Hurricane Protection Project. The USACE’s contractor, Eastman A

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Jacksonville District, said in its latest release that the Sunny Isles Beach renourishment project is set to kick off.

The $8.6 million project is part of the Miami-Dade County Beach Erosion Control and Hurricane Protection Project.

The USACE’s contractor, Eastman Aggregate Enterprises, LLC of Lake Worth, Florida, will place approximately 140,000 cubic yards of sand on more than 4,400 feet of critically eroded shoreline in two locations, including both sides of the Newport Pier and at the north end of the city.

Placement of sand on the beach is scheduled to start today, October 31, and beach fill operations are expected to be in full swing by November 6.

Both the area north of the pier and the area to the south of the pier are scheduled for completion in December 2017.

Work at the north end of the project is scheduled to begin before the end of the year, with completion in May 2018.

Eastman Aggregates is scheduled to mobilize equipment at the north access and begin work on the base contract at the northern end of the city before the end of the year.

The federal project, led by the U.S. Army Corps of Engineers, in partnership with Miami-Dade County, the City of Sunny Isles Beach and the Florida Department of Environmental Protection, is cost-shared between the federal government (62.7%), Miami-Dade County (19.3%) and the state of Florida (18%).

[mappress mapid=”24571″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free