DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Kingussie Flood Alleviation Channel Works in Full Swing
Business & Finance

November 8, 2017 · about 8 years ago

Kingussie Flood Alleviation Channel Works in Full Swing

The Highland Council and Pitmain Estate announced today that the final phase of the work to construct the Kingussie Flood Alleviation Channel is now underway. The jointly-funded project between the Council and Pitmain Estate is located on the estate’s land above the village of Kingussie. McGowan Ltd

2 minutes read
  • LinkedIn
  • X
  • Email

The Highland Council and Pitmain Estate announced today that the final phase of the work to construct the Kingussie Flood Alleviation Channel is now underway.

The jointly-funded project between the Council and Pitmain Estate is located on the estate’s land above the village of Kingussie.

McGowan Ltd. of Aviemore carried out phase 1 of the construction in June and July. This phase saw the formation of a section of the diversion channel between the Allt Mor and Loch Gynack.

The contractors are now back on site for phase 2, which includes the construction of the main offtake weir on the Allt Mor. This will direct a proportion of the flow from the main river, via the diversion channel, into Loch Gynack where it will then be released at a controlled rate back into the River Gynack.

Council Convenor Bill Lobban , one of four councilors representing the Badenoch and Strathspey Ward said: “ Flooding in Kingussie due to the Gynack Burn continues to be a serious problem and I am very pleased to see these works are progressing. Once complete the scheme will help to reduce the frequency and severity of flooding and will protect property with the added benefit of increasing energy generation. ”

Although weather dependent, the work program is expected to be complete, and the scheme in operation, in five to seven weeks, reported the Highland Council.

This project is jointly funded 50:50 by the Highland Council and Pitmain Estate, as part of its commitment to reduce flood risk in Kingussie as set out in the Local Flood Risk Management Plan for the Findhorn, Nairn and Speyside Local Plan District.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free