DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Port of Mackay Breakwaters in Need of Repair
Business & Finance

December 5, 2017 · about 8 years ago

Port of Mackay Breakwaters in Need of Repair

North Queensland Bulk Ports (NQBP) are about to close the Port of Mackay breakwater to all vehicle traffic after new engineering analysis revealed significant damage to the structure. NQBP General Manager Engineering and Development, Rochelle Macdonald, said that initial assessments indicated the br

1 minutes read
  • LinkedIn
  • X
  • Email

North Queensland Bulk Ports (NQBP) are about to close the Port of Mackay breakwater to all vehicle traffic after new engineering analysis revealed significant damage to the structure.

NQBP General Manager Engineering and Development, Rochelle Macdonald , said that initial assessments indicated the breakwaters had escaped the worst of the Tropical Cyclone (TC) Debbie with minimal damage.

“ Further investigations, including 3D laser scanning, revealed the damage was worse than first thought. The Southern Breakwater in particular has suffered damage to the slope facing the sea ,” Dr Macdonald added.

“Like so many others in the region, TC Debbie delivered a powerful blow to our east coast operations ,” Dr Macdonald said. “ While there is no question about the safety of the breakwaters, repairs are essential to ensure their integrity for future cyclone seasons.”

According to Dr Macdonald, due to the nature of the works traffic, including cars and motorbikes, will be unable to access the Southern Breakwater during the repairs. “ Works are due to start in January. Our target is to have the repairs completed by the end of 2018.”

Overall, the project includes the supply and placement of 80,000 to 90,000 tonnes of rock for the breakwater project. NQBP estimates that the cost of the work will be around $12 million, with the tender process to be finalized in the coming weeks.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free