DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Pleasant Point Shoreline Protection Project up for Comment
Business & Finance

January 29, 2018 · about 8 years ago

Pleasant Point Shoreline Protection Project up for Comment

The U.S. Army Corps of Engineers, New England District, is working on a project that will stabilize approximately 1,500 feet of shoreline at the Pleasant Point Reservation home to members of the federally recognized Passamaquoddy Tribe. According to the Corps, the purpose of the proposed project is

1 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, New England District, is working on a project that will stabilize approximately 1,500 feet of shoreline at the Pleasant Point Reservation home to members of the federally recognized Passamaquoddy Tribe.

According to the Corps, the purpose of the proposed project is to prevent ongoing shoreline erosion in front of tribal housing, a church and a senior center at the Pleasant Point Reservation by constructing a 1,500 ft. long rip-rap revetment.

If the areas are not protected from further shoreline erosion, there will be adverse impacts to the tribal owned facilities, USACE reported.

The 36 ft. wide stone rip-rap revetment design consists of a geotextile fabric overlain by an 18-inch layer of core stone, an 18-inch layer of under stone and a 42-inch thick layer of armor stone rip-rap on a 1:1.5 vertical to horizontal slope.

The proposed revetment will tie into the southern section of a newly constructed 300 ft. revetment in front of the tribal owned waste water treatment plant.

The construction project is expected to take four to six months.

Deadline for sending comments on the proposed scheme is February 27, 2018.

[mappress mapid=”24816″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free