DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Savannah Harbor Expansion Project Reaching Midway Point
Business & Finance

February 5, 2018 · about 8 years ago

Savannah Harbor Expansion Project Reaching Midway Point

At today’s Georgia Foreign Trade Conference, Georgia Ports Authority Executive Director, Griff Lynch, announced that Savannah’s outer harbor dredging will be finished in March, bringing the Savannah Harbor Expansion Project (SHEP) to 50 percent completion. Deepening the inner harbor should be comple

1 minutes read
  • LinkedIn
  • X
  • Email

At today’s Georgia Foreign Trade Conference, Georgia Ports Authority Executive Director, Griff Lynch, announced that Savannah’s outer harbor dredging will be finished in March, bringing the Savannah Harbor Expansion Project (SHEP) to 50 percent completion.

Deepening the inner harbor should be complete by late 2021, allowing Neo-Panamax vessels to take on more cargo and transit the river with greater scheduling flexibility, according to the official announcement.

“ With the project moving forward, the fiscal argument for the Savannah Harbor deepening grows stronger and stronger as more customers choose Georgia as a gateway to serve the Southeast ,” Lynch said.

“The ability for these ships to take on heavier export loads will mean greater efficiency and lower costs for American producers.”

Lynch also provided an overview of GPA’s 2028 Plan that calls for 42 ship-to-shore cranes, 200 yard cranes, new RTG lanes and significant intermodal expansion in Savannah.

The GPA will soon open its second inland terminal in Northwest Georgia and break ground on the Mason Mega Rail project at Garden City Terminal.

Combined, both intermodal projects will open new markets while significantly reducing rail crossings and over the road freight through Savannah, Atlanta and beyond.

[mappress mapid=”24836″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free