DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Weeks Marine Kicks Off Wrightsville Beach Project
Business & Finance

February 14, 2018 · about 8 years ago

Weeks Marine Kicks Off Wrightsville Beach Project

The Wrightsville Beach Coastal Storm Damage Reduction Project, worth $9.4 million, is now officially underway. The project is Federally funded and under the supervision of the U.S. Army Corps of Engineers, the Town of Wrightsville Beach said in its latest announcement. Earlier this month, Weeks Mari

1 minutes read
  • LinkedIn
  • X
  • Email

The Wrightsville Beach Coastal Storm Damage Reduction Project, worth $9.4 million, is now officially underway.

The project is Federally funded and under the supervision of the U.S. Army Corps of Engineers, the Town of Wrightsville Beach said in its latest announcement.

Earlier this month, Weeks Marine, Inc. began mobilization operations including installation of large pipes on the beach and prepping beach walkovers.

The actual dredging and pumping of sand started this week.

The contractor is currently working in an area north of the Blockade Runner Beach Resort and end just north of the Holiday Inn Resort. Each day, a work area of approximately 1,200 feet will be fenced off and work will continue 24 hours a day, 7 days a week.

The dredging and beach fill portion of the project will take approximately 30 days, placing around 700,000 cubic yards of sand onto the beach.

Following the dredging and beach fill portion of the project, there will be a 10 to 12 day demobilization period.

Work is scheduled to be completed on or before March 31, the city said.

[mappress mapid=”24863″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free