Dredging Today
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Offshore Wind
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Dredging Work Wrapped Up for Sunshine Airport Expansion
Business & Finance

September 24, 2018 · about 7 years ago

Dredging Work Wrapped Up for Sunshine Airport Expansion

The Sunshine Coast Airport expansion project has reached another significant milestone, with the completion of sand dredging and pumping operations ahead of schedule, the Sunshine Coast Regional Council said in its latest release. Around 1.3 million cubic meters of sand is now on site and will form

2 minutes read
  • LinkedIn
  • X
  • Email

The Sunshine Coast Airport expansion project has reached another significant milestone, with the completion of sand dredging and pumping operations ahead of schedule, the Sunshine Coast Regional Council said in its latest release.

Around 1.3 million cubic meters of sand is now on site and will form the foundation of the runway which remains on track to be completed by Christmas 2020.

Sunshine Coast Mayor, Mark Jamieson, said that finishing the dredging phase of construction was a very important step for the $303 million expansion project.

“Finishing this program of work ahead of time is a great credit to everyone involved, ” Mayor Jamieson said.

“I’d like to thank John Holland, the Dredging International crews and the airport expansion project team for managing this huge exercise so smoothly.

“Based on the progress to date, I have every confidence that we will have the pipeline removed and the beach rehabilitated before November 1 – the official start of the turtle nesting season.”

Mayor Jamieson added that the Sunshine Coast Airport Expansion project was forging ahead at a rate of knots.

“ Pumping the sand from the Spitfire Channel in Moreton Bay and transporting it to the Sunshine Coast by the Nile River dredge has proven to be an outstanding success ,” Jamieson added.

“If this sand had to be transported by road, it would take approximately 12 months to get it on site, with 350 truck movements per day (175 in each direction) or approximately one every 1.7 minutes. Our off-shore solution has seen the same job done in under three months.

“But most importantly, we have avoided 12 months’ of truck movements through towns like Bli Bli, which are on the haul route.”

Mayor Jamieson also said that the airport runway expansion was Sunshine Coast Council’s single largest construction project and would deliver a wealth of benefits to the region.

Project facts

Reach the Dredging Today industry in one go!

Dredging Today is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1EXCLUSIVE: IHC Equipment extends operational life of TSHD Biesbosch
  2. 2Dredging underway at Beach Haven West Complex
  3. 3Isle of Palms dredging update: Marinex makes steady progress
  4. 4GLDD’s dredger Liberty Island kicks off Buxton beach nourishment

Related articles

DEME’s nine-month turnover tops 3 billion euros
Business & Finance

DEME’s nine-month turnover tops 3 billion euros

about 8 months ago

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free

Related news

DEME’s nine-month turnover tops 3 billion euros
Business & Finance

DEME’s nine-month turnover tops 3 billion euros

about 8 months ago