MidCoast Council, NSW, Australia, has just announced that their dredging operations in the Lower Myall River are progressing according to schedule with 27,000 cubic metres of sand removed from the eastern channel so far.
The contractor, Dredging Solutions Pty Ltd, is now one month in to the 27 week project that will remove a total of 120,000 cubic metres of sand from the channel.