Work on the S. Maradhoo Harbor breakwater reconstruction scheme is nearing its completion, with overall 92% project progress, the Maldives Transport and Contracting Company Plc (MTCC) reports.
“Revetment works for the project are currently ongoing, with 65% completion. We also completed paving works of 1,975 sqm needed for the project in June 2020,” the company stated.