J.F. Brennan Company, Inc. is working in full swing to complete the Fountain Lake restoration project.
According to Shell Rock River Watershed District (SRRWD), the past week was another productive one for crews working on this dredging program.

J.F. Brennan Company, Inc. is working in full swing to complete the Fountain Lake restoration project.
According to Shell Rock River Watershed District (SRRWD), the past week was another productive one for crews working on this dredging program.
Dredging Today is read by thousands of professionals every day.
Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.
Join thousands of industry professionals who start their day with our newsletter.
The dredging operations are part of the overall phase two of the Fountain Lake restoration project in Albert Lea, MN.
So far, the contractor dredged over 225,500 cubic yards of material from the Main Bay and Dane’s Bay, reports SRRWD.
The first phase included removal of over 700,000 cubic yards of sediment out of the Edgewater Bay.
After the second phase of dredging, the third and final phase will complete the Fountain Lake restoration project.
The third phase includes Main Bay (East Basin), Bancroft Channel and parts of Bancroft Bay.