Dredging Today
JobsNewsletter
Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Offshore Wind
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs

© 2026 Navingo. All rights reserved.

Home›Business development›First stage of Lower Vasse River dredging wraps up
Business development

June 15, 2022 · about 4 years ago

First stage of Lower Vasse River dredging wraps up

The City of Busselton has recently completed the first stage of sediment removal in the Lower Vasse River with the aim to improve water quality. Approximately 600 tonnes of sediment was removed over seven weeks. The area dredged spanned from the Causeway Road Bridge to upstream from the pedestrian b

2 minutes read
  • LinkedIn
  • X
  • Email
First stage of Lower Vasse River dredging wraps up

The City of Busselton has recently completed the first stage of sediment removal in the Lower Vasse River with the aim to improve water quality.

Approximately 600 tonnes of sediment was removed over seven weeks. The area dredged spanned from the Causeway Road Bridge to upstream from the pedestrian bridge, on Peel Terrace.

Sediment will continue to dewater for an additional 6-8 weeks whilst being tested for the presence of acid sulfate soil, treated if required and transported off site for reuse. It is expected these works will be completed by August 2022.

Water quality in the river was closely monitored for the duration of the works to ensure no detrimental impacts from the dredging operation and the dewatering of the sediment occurred.

Mayor Grant Henley said: “This first stage of sediment removal in the Lower Vasse River has been widely successful, with a large quantity of sediment removed. This represents a significant amount of nutrients which won’t be released next summer, going towards improving water quality in the river”.

A thick layer of nutrient-rich, fine organic sediments has accumulated throughout the Lower Vasse River, providing an internal source of nutrients that contributes to algal growth and poor water quality in summer.

While sediment removal alone is not expected to prevent algal blooms occurring in the river, it is an important step for improving water quality.

Planning for additional sediment removal is progressing, with a future stage planned for later this year.

A funding application was also submitted to the WA Government Community Stewardship Program for additional sediment removal in 2023.

Reach the Dredging Today industry in one go!

Dredging Today is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Filed under

Business development

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1VIDEO: Italdraghe SGT 200 CSD raises the bar in Guyana
  2. 2Manson nabs $12.9M Oakland dredging deal
  3. 3Maryland DNR provides funding for 24 public boating projects
  4. 4Queensland Government: Upper Warrill Creek flood resilience project begins

Related articles

Marinex wins Brunswick dredging contract
Business development

Marinex wins Brunswick dredging contract

13 days ago

PHOTO OF THE DAY: Maldon Harbor dredging in full swing
Business development

PHOTO OF THE DAY: Maldon Harbor dredging in full swing

13 days ago

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free

Related news

Marinex wins Brunswick dredging contract
Business development

Marinex wins Brunswick dredging contract

13 days ago
PHOTO OF THE DAY: Maldon Harbor dredging in full swing
Business development

PHOTO OF THE DAY: Maldon Harbor dredging in full swing

13 days ago