The Army Corps’ New England District Planning Division performed maintenance dredging which hydraulically removed approximately 118,000 cubic yards of sand from Cape Cod Canal.

Share this article
The Army Corps’ New England District Planning Division performed maintenance dredging which hydraulically removed approximately 118,000 cubic yards of sand from Cape Cod Canal.
Dredging Today is read by thousands of professionals every day.
Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.
Join thousands of industry professionals who start their day with our newsletter.
The sand was then pumped onto Town Neck Beach in Sandwich, MA. Additional sand will be placed on Town Neck Beach as part of the Cape Cod Canal Section 111 Shore Damage Mitigation Project.
This project will provide further shoreline protection to Town Neck Beach along with the 600+ acre salt marsh behind it. Up to 387,000 cubic yards will be dredged from the Scusset Borrow Site, off of Scusset Beach Reservation, and placed onto the beach.
A dune and berm will be constructed on Town Neck Beach as part of the project to protect the beach’s properties and natural resources.
USACE is currently in the design phase for the project with construction expected to begin in October 2024.
10 days ago
about 2 years ago
The Army Corps’ New England District Planning Division performed maintenance dredging which hydraulically removed approximately 118,000 cubic yards of sand from Cape Cod Canal. The sand was then pumped onto Town Neck Beach in Sandwich, MA. Additional sand will be placed on Town Neck Beach as part of