The Town of Barnstable’s contractor, AGM Marine Construction, will soon begin mobilizing equipment in preparation to start the Barnstable Harbor Mid-Entrance Channel and Blish Point Boat Ramp Dredging Project.
Dredging operations are anticipated to begin on Monday, December 22.
“ Weather pending, dredging activities will be on going during low and mid tides; however a brief pause of work will be observed from December 24 – 26, 2025 ,” according to an official statement.
Dredging work is expected to be completed by January 31, 2026, the Town said.
The project is partially funded by a Fiscal Year 2026 Commonwealth of Massachusetts Dredging Grant totaling $519,000.