DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Port Expansion›Jan De Nul gets green light to start USD 122 million dredging project in Brazil
Port Expansion

July 23, 2026 · 29 days ago

Jan De Nul gets green light to start USD 122 million dredging project in Brazil

The Santos Port Authority (APS) has authorised the start of the project to deepen the navigation channel of the Port of Santos, Brazil, from 15 meters to 16 meters. Back in June, it was announced that Jan de Nul do Brasil (part of the Jan De Nul Group) won the USD 122.3 million contract to […

1 minutes read
  • LinkedIn
  • X
  • Email
Jan De Nul gets green light to start USD 122 million dredging project in Brazil
Source: Santos Port Authority/Illustration

The Santos Port Authority (APS) has authorised the start of the project to deepen the navigation channel of the Port of Santos, Brazil, from 15 meters to 16 meters.

Back in June, it was announced that Jan de Nul do Brasil (part of the Jan De Nul Group) won the USD 122.3 million contract to deepen the channel.

The contract award was suspended on 16 June after DTA Engenharia, another bidder in the tender, issued a legal challenge, alleging that Jan De Nul’s bid may have been too low and not economically viable.

Jan De Nul and APS appealed the injunction, which was ultimately overturned on 15 July, allowing for the project to proceed.

With the issuance of the work order by APS, Jan de Nul began the environmental impact studies necessary to obtain the environmental license for the project from IBAMA (Brazilian Institute of Environment and Renewable Natural Resources). The expected timeframe for the completion of this first phase is up to 21 months.

The five-year canal deepening project includes the stages of environmental licensing of the undertaking; preparation of the Basic and Executive Projects; execution of the deepening dredging; and execution of maintenance dredging of the new clearance for a period of up to two years.

The project aims to allow the port to accommodate the larger draught requirements of modern container vessels and expand the port complex’s cargo capacity, according to APS.

Related Articles

Business development

BREAKING NEWS: Jan De Nul wins Port of Santos dredging contract

1 min read

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Port Expansion

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dredging work underway for Iraq’s first LNG import terminal
  2. 2Jan De Nul: Spotlight on Bankbusters project
  3. 3Marina de Lagos expansion: New berths enter final stretch
  4. 4Secretary Dizon: President Marcos wants all waterways in Naga City dredged

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free