The City of Moreton Bay has just completed its biggest dredging project within the Pacific Harbor Canal Estate at Banksia Beach.
It has been a mammoth task with about 80,000 cubic meters of sediment removed from Skippers Canal and pumped via a 7km temporary pipeline, across the Passage, to City of Moreton Bay’s Dredged Material Management Facility at Ningi.
The work started in mid-2025 and has taken eight months to complete.
The City said that the next major maintenance dredging project will be in 10-20 years.